| St. Christopher's By the Sea |
![]() Chatham, Massachusetts |
Would you like us Would you like to know when the St. Christopher's web site is updated? Simply send us an email by clicking here and we will notify you by email when new items or pages have been added to the site.
|
st. Christopher's constructiona photo diary September 21, 2009
We're almost there!
June 12, 2009 'Ribs' of reception area take shape
Assitant Rector Gail Smith delighted in the similarity to a boat's ribs as the roof over the new church reception area, so she snapped this picture. With every passing day, construction gives more and more of a sense of what the church will look like when completed. March 12, 2009 Foundation concrete pours started
February 22, 2009 'Pit' filling in; concrete pours begin
For the past several days, workers have been pouring concrete into the pile cap forms and footings that dot the huge hole below the courtyard area. Workers from Robert Our Co. are filling in around the caps (top, right). That should prove to be a welcome sight! Additionally, workers are moving large steel panels up against the foundation for added support (below, right). Building Committee Chairman Bruce Wood reports that at some point in the next several weeks, a deep pit for the new elevator will be put into place. Work continues in the Sanctuary as well, especially in the old Narthex area. Two new stairways are being built – one to the bell tower and the other an emergency exit stairway leading out into the courtyard area. Workers also have torn out much of the plaster and lath from the rear wall of the Sanctuary, revealing the
so-called “balloon framing” construction techniques prevalent in the 1800s.
Balloon framing did not require highly skilled carpenters and was quite flimsy.
This technique got its name from skilled carpenters of the day, who called it no
more substantial than a balloon! Most communities have outlawed balloon framing
because of the fire danger it poses – it provides a path for fire to travel from
floor to
floor.
February 4, 2009 Piles work continues; some go down 42 feet
moving day for worship space
What to do on that special day?
Meanwhile, Rector Brian W. McGurk was trying to figure out how to mark the day.
“How do we make it special?” he repeatedly asked the staff. “How do we make it
meaningful?” Even the best-laid plans…
But events
always seem to have their own way. The final push
Voluntee
We come together
On Sunday, the congregation gathered in the Parish Hall for worship.
(Photos-- Top, Brian shares
communion "in the round" in temporary sacred space in the Parish Hall. Middle,
volunteers work on Friday to prepare the Sanctuary in the Parish Hall. Bottom,
Linus Decker paints the walls of the Parish Hall.)
January 18, 2008 Crib towers to support Sanctuary
Last week, workers
successfully removed asbestos from the Sanctuary. Outside, they are shoring up
the Sanctuary as they prepare to install piles next to and under
January 7, 2008 Organ, pews dismantled; soil work continues
On Monday, Jan. 5, workers
from Andrew Organ Co. of Methuen began to take apart the tracker organ in the
Sanctuary. Some parts will be stored, although most of
For more pictures, see our Construction page. Want email for St. Christopher's construction updates? Please email StChristophers@comcast.net. Decem ber 18, 2008Contaminated soil, water issues addressed
Over the weekend of Dec. 13-14, Building Committee Chairman Bruce Wood
announced at each worship service what some had feared – workers have discovered
contaminated soil and groundwater on the building site. (Photo above: Workers poured concrete into large holes filled with rebar on Wednesday, Dec. 17. The filled-in holes will be the base of new support columns. ) December 16, 2008
A hazardous waste container arrives at the rear of the church on Dec. 16. Adler Tank Rentals is based in New Jersey but has a tank storage facility and an office in Randolph, Mass. November 29, 2008
Installing new pilings will begin Monday, Dec. 1, according to Bruce Wood, chairman of the Building Committee. Each pile will be hammered into the ground about 35-40 feet deep. Workers also will pump standing and ground water into the courtyard area. When the water is pumped off-site, it will pass through a large trailer containing a filtering system so that it will be free of silt, sand and clay. November 5, 2008
Workers have dug a large hole in the courtyard down to the water table (left) and continue excavation in the undercroft area (below). Crews will dig deeper when they begin to install pilings and concrete foundation components, scheduled for Nov. 17. Please note that Delphi Construction managers have cut an opening in the portico screen so all you “sidewalk superintendents” can regularly check on our progress.
October 29, 2008
Note the yards of topsoil in the old courtyard (above). This week workers are clearing asbestos in the old office complex, consignment shop and library. Below - And the walls come tumbling down! Brian checks the area that used to house the consignment shop and library. The space will be renovated into a new office complex.
October 22, 2008
Movers from Fancy’s in Chatham move the contents from the library and the Gift & Consignment Shop into storage on Monday and Tuesday. They're parked on what used to be the back yard. October 21, 2008 Workers from Robert B. Our Co., Inc. continue interior demolition as they prepare for the asbestos removal phase, which begins next week. Meanwhile, Ali Crockett, superintendent of Buildings and Grounds, is beginning to plan for “transition, phase 2” which involves moving from the Sanctuary into the Parish Hall. The last service in the Sanctuary is Jan. 4. October 15, 2008 Out with the old
The rector's office is gone now. In its place, workers have built a temporary staircase as an emergency exit from the Sanctuary. In the foreground is what remains of the courtyard. Below, the library has been packed up and will soon be closed for asbestos removal. (Photos by Tim Weller)
October 7, 2008 Clearing the way
On Tuesday, Oct. 7, construction crews from Robert B. Our Construction Co. demolished the rear part of the church, which used to house staff offices and Brian’s second-floor office. Gone in a day! At right, Brian wears his personalized hard hat. Brian’s temporary new office is in a second-floor classroom above the Parish Hall. Crews have cleared trees and bushes in the courtyard and in the back yard, although the Memorial Garden is protected by a screened fence. The Gift and Consignment Shop will close at the end of the week as demolition work continues in that area.
Rector Brian McGurk stands on the roof of the Parish Hall to watch as his former office is demolished to make way for new construction on St. Christopher's Church. September 23, 2008 CONSTRUCTION BEGINS!
Workers started work in earnest on Sept. 23, walling in the back yard of the church and blocking off the rear entrance. September 23, 2008
Staff members Ilene Bendas and Jamie Chalker -- in vain -- try to break into the courtyard. Construction officially began Sept. 23 when workers installed a six-foot high chain link around the courtyard and backyard.
Think you can come through the back door? Think again! Parish Nurse Priscilla Chick shows how workers have walled off the back door. (Photos by Tim Weller)
|
|
|
|